Residential Solar Installation Process

We make the Solar Installation Process smooth and easy.  We update and walk you through every step of the process.

  • System Design - A rendering of panels layout - 1 day

  • Engineering - Incorporates system design with electrical code drawings. 1 - 2 weeks

  • HOA Approval - submitt drawings and engineering (they have to approve by law)

  • Permitting - County reviews engineering and issues permit.  3 -4 weeks

  • Installation - Where design and engineering become a reality. 2 - 3 days

  • Inspection - County inspector reviews installation for code compliance - 1 week

  • Interconnection - Power Company inspection and agreement. 3-4 weeks

  • Commissioning System - Turn on system and monitoring. 1 -2 days